why big projects’ final bill always makes us ill: keenan - gas grill with cast iron grates
by:Longzhao BBQ
2020-04-25
Yesterday, I read the latest news about the delay in the expansion of the New York University subway, thinking of my gas stove.
When my wife and I bought our house, we saw a lot of things on the stove, a half-priced showroom model with seven stoves, an extra one
Wide range of oven and stainless steel finish with cast iron grille.
In order to use it, we need to open a gas pipe to the kitchen.
We called a gas company recommended by a contractor friend who said it would cost $150 and it would take an hour or two.
We really wanted the stove so we didn't ask any more questions.
We brought it home that day.
It turns out that our existing gas equipment is not properly ventilated, so no gas work can be done at all until the chimney lining is replaced.
Except for the chimney itself, collapsed bricks are everywhere.
This means it's easier to cover the chimney with direct heating and replace our aging water heater and stovevented models.
The job will take up to three workers in two working days.
The bill is thousands of dollars.
The work is necessary and the cost may be inevitable.
However, our schedule and budget have been ruined.
What does this have to do with transit buildings? Lots, actually.
In 2009, Matti bhariatycki, a professor at the University of Toronto, made a comment explaining why large transportation infrastructure projects around the world always seem to be behind schedule and out of budget.
Anyone who has seen the same phenomenon in home decoration projects like me will be familiar with his conclusion.
Bhariatycki studied academic research and government audit reports from five continents covering hundreds of construction projects.
He found that the most common point of academic research is the political factor of "cross-border. . .
The line between error and deception.
"Once a project is approved and implemented, it is difficult to cancel, so by cheating and subconscious cognitive bias, when politicians or bureaucrats come up with a project, their motivation is to make it look attractive.
They found and put forward very optimistic time and cost estimates.
This is in line with the different causes of the issues most frequently cited in the audit report by asiiaycki --
One part stems from the conventional practice of approving projects, completing funding arrangements, budgets and schedules before detailed engineering and design studies are completed. Two-
Thirty reports from the study found that "scope changes" and "change orders" were significant in driving up costs.
From a real point of view, these results
The details of the life of the construction project and are aware of what additional work and unforeseen obstacles are involved.
When you sign a project first and then look at the details of it, they are all sorts of surprises you come across.
The opening of the York University Metro extension project has been delayed for a year and we have heard that it may be further delayed due to funding delays, tunnel issues, weather issues and the complexity of the contractor.
These problems seem to be avoided or foreseen by better planning at the initial stage of the project.
After reading the study of bhariatycki, these questions do not seem to be surprising.
Our newly elected mayor, John Torley, has promised to keep track of progress by holding weekly meetings to control the crazy budget and schedule.
This is good news.
Better performance monitoring and enhanced accountability are steps that can help solve building problems, writes bhariatycki.
Bad news: The most common pitfalls in the Conservative Party's own tent transport program seem painfully obvious.
During the election, the Conservative Party presented a specific budget and a positive timetable for his smart track proposal.
In response to questions about technical challenges, the Conservative Party admitted that in the detailed engineering and design studies completed later, questions such as the number of tunnels involved would be sorted out.
It reminds me of how I decided to want a 7-
Before I double check the actual steps of installing the burner in my house, the burner range.
Whether you're installing a kitchen infrastructure or building a transportation infrastructure, "buy it first and learn later" is a risky strategy.
What we see isyet again —
Again on the New York Metro Archives.
We have the risk of duplication as we move on to the next project.
This is another way the traffic project reminds me of the stove: If you don't pay attention to the details of what you are doing, you will be burned again and again.
Edward Keenan wrote on the city issue. ca .